  • 14,332 homes, net, 1996–2025

    Homes permitted, of All 1158 dated housing-permit records, 1996–2025

    Fact— show source

    Direct from an identified authoritative or primary source.

    Housing Permits 1996 - Present · City of Cambridge · grouped by permit year and by neighbourhood; totals only · recorded August 26, 2026

  • 4,040 homes, 2019–2025

    Homes completed, of All 1,553 certificates of occupancy on record

    Fact— show source

    Direct from an identified authoritative or primary source.

    Certificates of Occupancy · City of Cambridge, Inspectional Services · grouped by issue year, certificate type and temporary flag · recorded October 10, 2026

  • 13 neighbourhoods, ranked

    Neighborhood distribution, of 14,332 homes net across all neighbourhoods, 1996–2025

    Calculated— show source

    The formula uses identified inputs and the method is reproducible.

    Method: ranking of the published per-neighbourhood sums; the sums themselves are the City's figures

    Housing Permits 1996 - Present · City of Cambridge · grouped by permit year and by neighbourhood; totals only · recorded August 26, 2026

  • 1,084 homes removed

    Homes removed, of 22,249 homes permitted over the same period

    Fact— show source

    Direct from an identified authoritative or primary source.

    Housing Permits 1996 - Present · City of Cambridge · grouped by permit year and by neighbourhood; totals only · recorded August 26, 2026

  • 12.8%, 67 set-aside projects

    Affordable homes in the development record, of 7,750 homes across 67 set-aside projects, 2011–2025

    Calculated— show source

    The formula uses identified inputs and the method is reproducible.

    Method: affordable homes divided by all homes, over the projects publishing both counts

    Development Log — current edition and historical additional details · City of Cambridge · grouped on unit counts; blanks counted, never read as zero · recorded July 30, 2026

  • 3+ bedrooms: 5% to 16%

    Bedroom mix, of 842 homes approved under the prior ordinance and 49 under the revised one

    Fact— show source

    Direct from an identified authoritative or primary source.

    2018 Inclusionary Housing Report · Cambridge Community Development Department · Figure 5, page 8 · recorded June 30, 2018 · verified August 21, 2026

Two questions that look like one

How many affordable homes get built, and what share of new housing is affordable, are different questions, and only the first can be answered from what Cambridge publishes. Two thirds of current projects record no affordable-home count at all, and a blank may mean none or may mean unrecorded. Every figure on this page therefore carries the number of projects it is computed over, and the number left out.

The requirement is 20 per cent of dwelling unit net floor area, for building permits issued after 2017-06-30. Every affordability figure the City publishes is a count of homes. Affordable homes are typically smaller than market ones, so a share of floor area and a share of homes are different quantities, and neither sets a bound on the other. Floor area is not published for each project, so this page states both in their own terms and does not divide one by the other.

Neighborhood distribution

homes · 13 neighbourhoods, ranked highest first

Neighborhood distribution — homes, by neighbourhood
neighbourhoodhomes
1 - East Cambridge5,954
11 - North Cambridge3,084
12 - Cambridge Highlands1,504
5 - Cambridgeport1,046
2 - Area 2/MIT897
4 - The Port590
9 - Neighborhood Nine563
7 - Riverside553
3 - Wellington-Harrington156
8 - Baldwin145
6 - Mid-Cambridge103
13 - Strawberry Hill39
10 - West Cambridge-26
Fact— show source

Direct from an identified authoritative or primary source.

Housing Permits 1996 - Present · City of Cambridge · grouped by permit year and by neighbourhood; totals only · recorded August 26, 2026

The other account of the same city

The Development Log counts homes in large tracked projects and is republished each quarter. This page counts homes in the permit record, which covers every housing permit since 1996. The two do not agree, and neither is wrong: they count different things. Both are shown here so you can see the difference for yourself.

Read the development recordWho qualifies, by incomeEvery source behind these figures

All join

All join.All work together.

Two ways in, and they are different things. Joining us is free and takes a minute. Membership funds the work and buys no influence over what the record says.

People out in Cambridge: front porches in flower, a street of shopfronts, a park lawn and a shaded public shelter.